Freezing Donations; Continuing The Project
Published on March 29, 2021 by James Vorderbruggen
Hello all, Over the last year, we have been mainly focused on building a pilot network in The Port, Cambridge. Due to a combination of limited organizing capacity, lack of interest on the ground, and technical hurdles, that project never re...
Somerville Library Install With Culture House
Published on January 10, 2021 by James Vorderbruggen
Yesterday, we completed another secure wireless hot-spot install for Culture House. This time, the hot-spot is available at the Somerville public library. Culture House was constructing an outdoor pavilion there for Somerville residents and...
Cambridge Port Pilot -- Slow and Steady
Published on September 8, 2020 by James Vorderbruggen
Summer UpdateIt's been a long, socially distanced summer, but we've still found ways to mesh. Since last update we've:Started work on a 6-node pilot in Cambridge Port. While this project has taken a while to get off the ground, we've alread...
2 New Installs and a Python Package
Published on May 6, 2020 by James Vorderbruggen
Hello to all of our lovely backers! It's been a while since I gave an update, and we've been quite busy for the last few months. A couple things we've been doing since last update:We installed two new secure wireless hot-spots. Many than...
We're legit!
Published on February 3, 2020 by James Vorderbruggen
Today, we finally filed our paperwork with a local credit union, and are ready to accept donations and membership dues! Handling our finances transparently and collaboratively will help facilitate our next steps to building a distributed...